Case study: You are the project manager for the world's #1 microblogging company – Chitter. Your project objective is to upgrade the software application to the latest version.
The following are the critical success criteria for your project:
- Since millions of users are connected, there has to be zero downtime for the application.
- Preserve existing customer data and migrate minimal new data.
The following assumptions will be made:
Consider a small subset of tasks from the whole project, pertinent to what you've learned in this chapter.
Breakdown of work
Please enter the following task list into a new blank Project file so that you can follow along. Practice makes perfect!
- Stage several trials for the new application
- Launch the project on the production server
- Migrate consumer data
- New branding data migration
- Set up the production server infrastructure
- Complete production...