PostgreSQL 9 High Availability Cookbook

You're reading from   PostgreSQL 9 High Availability Cookbook Over 100 recipes to design and implement a highly available server with the advanced features of PostgreSQL.

Arrow left icon
Product type Paperback
Published in Jul 2014
Publisher Packt
ISBN-13 9781849516969
Length 398 pages
Edition 1st Edition
Arrow right icon
Author (1):
Arrow left icon
Shaun Thomas Shaun Thomas
Author Profile Icon Shaun Thomas
Shaun Thomas
Arrow right icon
View More author details
Toc

Table of Contents (12) Chapters Close

Preface 1. Hardware Planning FREE CHAPTER 2. Handling and Avoiding Downtime 3. Pooling Resources 4. Troubleshooting 5. Monitoring 6. Replication 7. Replication Management Tools 8. Advanced Stack 9. Cluster Control 10. Data Distribution Index

Planning for redundancy

Redundancy means having a spare. A spare for what? Everything. Every single part, from motherboard to chassis, power supply to network cable, disk space to throughput, should have at least one piece of excess equipment or capacity available for immediate use. Let's go through as many of these as we can imagine, before we do anything that might depend on something we bought.

Getting ready

Fire up your favorite spreadsheet program; we'll be using it to keep track of all the parts that go into the server, and any capacity concerns. If you don't have one, Open Office and Libre Office are good free alternatives for building these spreadsheets. Subsequent sections will help determine most of the row contents.

How to do it...

We simply need to produce a hardware spreadsheet to track our purchase needs. We can do that with the following steps:

  1. Create a new spreadsheet for parts and details.
  2. Create a heading row with the following columns:
    • Type
    • Capacity
    • Supplier
    • Price
    • Count
    • Total cost
  3. Create a new row for each type of the following components:
    • Chassis
    • CPU
    • Hard Drive (3.5")
    • Hard Drive (2.5")
    • Hard Drive (SSD)
    • Motherboard
    • Network Card
    • Power Supply
    • RAID Controller
    • RAM
    • SAN
  4. In the Chassis row, under the Total cost column, enter the following formula: =D2*E2
  5. Copy and paste the formula into the Total Cost column for all the rows we created. The end result should look something like the following screenshot:
    How to do it...

How it works...

What we've done is prepare a spreadsheet that we can fill in with information collected from the rest of this chapter. We will have very long discussions regarding each part of the server we want to build, so we need a place to collect each decision we make along the way.

The heading column can include any other details you wish to retain about each part, but for the sake of simplicity, we are stuck to the bare minimum. This also goes for the parts we chose for each column. Depending on the vendor you select to supply your server, many of these decisions will already be made. It's still a good idea to include each component in case you need an emergency replacement.

The Total Cost column exists for one purpose: to itemize the cost of each part, multiplied by how many we will need to complete the server.

Tip

To make sure we account for the redundancy element of the spreadsheet, we strongly suggest inflating the number you use for the Count column, which will also increase the price automatically. This helps so we automatically include extra capacity in case something fails. If you would rather track this separately, add a Spare Count column to the spreadsheet instead.

We'll have discussions later as to failure rates of different types of hardware, which will influence how many excess components to allocate. Don't worry about that for now.

There's more...

It's also a very good idea to include a summary for all of our Total Cost columns, so we get an aggregate cost estimate for the whole server. To do that with our spreadsheet example, keep in mind that the Total Cost column is listed as column F.

To add a Sum Total column to your spreadsheet on row 15, column F, enter the formula =SUM(F2:F12). If you've added more columns, substitute for column F whichever column now represents the Total Cost. Likewise, if you have more than 13 rows of different parts, use a different row to represent your summary price than row 15.

See also

There are a lot of spreadsheet options available. Many corporations supply a copy of Microsoft Excel. However, if this is not the case, there are many alternatives as follows:

All of these options are free to use and popular enough that support and documentation are readily available.

You have been reading a chapter from
PostgreSQL 9 High Availability Cookbook
Published in: Jul 2014
Publisher: Packt
ISBN-13: 9781849516969
Register for a free Packt account to unlock a world of extra content!
A free Packt account unlocks extra newsletters, articles, discounted offers, and much more. Start advancing your knowledge today.
Unlock this book and the full library FREE for 7 days
Get unlimited access to 7000+ expert-authored eBooks and videos courses covering every tech area you can think of
Renews at $19.99/month. Cancel anytime