Appendix A
This appendix expands the 5 Content Tab from the 01 ART Readiness Workbook (V6.0) from the Scaled Agile Framework (SAFe) Program increment (PI) Planning Toolkit.
In the following table, you will see the key activities outlined as well as tasks/activities that are typically executed to meet the overall deliverable. Although the list is not comprehensive, you can use it as a template and refine and enhance each PI for specifics within your organization.
The dates make the following assumptions:
PI event start date |
6/6/23 |
Inspect and Adapt (I&A) date |
6/5/23 |
Number of iterations in PI |
Five |
Innovation and Planning (IP) iteration start date |
5/31/23 |
An additional column is displayed with the formula used to calculate...