- Your project work is ending and you are looking forward to meeting with your customer and showing them the result before closing the project. Which of the following is necessary before you can close out the project formally with their approval?
- Quality control
- Close procurement
- Validate scope
- Quality assurance
- Your team has worked extremely hard on the project and you have completed all the work necessary to close out your project formally and successfully. What kind of project closure has occurred?
- Starvation
- Extinction
- Integration
- Addition
- Which of the following project endings can best be described as an ending in which the project you are working on develops into a functional department or contributes to the ongoing operations of the organization?
- Addition
- Starvation
- Extinction
- Integration
- Your project has been a bit behind schedule and your team has...