- You are the project manager for a large installation project. Your key stakeholders are discussing what is needed to be accomplished to set up their new data center and have some specific ideas about what they want. What is the best document to collect all their requirements?
- Requirements list
- WBS
- Requirements traceability matrix
- Scope statement
- Which of the following is the best description of a WBS?
- Hierarchical decomposition of 100% scope of work
- Organizational chart for scope of work
- What will and will not be included in the scope of work
- An outline
- Bill is your sponsor, and he has come to you and asked for an overview of the work package you and your team have decomposed. He is concerned because your customer doesn’t really understand your WBS, and before they sign off on the baseline, they would like a clearer understanding of the scope of work...