Questions
Question 1
You have been assigned as the project manager for a large Six Sigma quality improvement project and the charter has been created. You invite multiple stakeholders to discuss the charter. What facilitation technique is best for this situation?
- Focus groups
- Meeting management
- Delphi technique
- Project initiation
Question 2
During the control risks process, you have collected work performance data and now have work performance information. What will this information be used for?
- To update the outcomes of risk reassessments
- To recommend corrective or preventative actions
- To communicate to stakeholders and support decision making
- To make sure all risks are being considered
Question 3
A large manufacturing project is underway. Your team has been informed that key stakeholders are confirming that quality requirements have been met by doing a walk through the plant. This is also known as which of the following...