- The CEO asks the developers to add a very important item to a Sprint that is in progress. What should the developers do? (Choose the best answer.)
a) Add the item to the Sprint Backlog immediately.
b) Add the item to the Sprint Backlog, but only if the item is in line with the Sprint Goal.
c) Add the item to the Sprint Backlog and drop an item of equal size.
d) Inform the Product Owner so that they can work with the CEO.
- True or False: When multiple teams work together on the same product, each team should maintain a separate Product Backlog.
a) True.
b) False.
- Which of the following provides the Scrum Team with an objective and overarching direction for the Sprint? (Choose one.)
a) The Sprint Backlog
b) The Sprint Goal
c) The Product Goal
d) The Definition of Done
- Halfway through the Sprint, the developers have already produced an Increment that is usable and Done. The stakeholders are very interested in reviewing the Increment as soon as possible. What should the...