Question 1
You have been assigned as the project manager for a large Six Sigma quality improvement project and the charter has been created. You invite multiple stakeholders to discuss the charter. What facilitation technique is best for this situation?
- Focus groups
- Meeting management
- Delphi technique
- Project initiation
Meeting management is the best answer here. Focus groups are coordinated around the scope definition, the Delphi technique is anonymous expert judgment, and project initiation is a process group.
Question 2
During the control risks process, you have collected work performance data and now have work performance information. What will this information be used for?
- A way to update the outcomes of risk reassessments
- A way to recommend corrective or preventative actions
- A way to communicate to stakeholders and support decision making
- A way to make sure all risks are being considered
Work performance information...