Creating and personalizing Change Management Sequential Activities
If you have configured Parallel Activities as described in the previous recipe, all activities will be set to the status of In Progress at the same time. If you need to serialize activities inside a Parallel Activity container you must use Sequential Activities.
This recipe will show you how to work with Sequential Activities inside a Parallel Activity container.
Getting ready
To create Sequential Activities in a Change Request Template open the SCSM 2016 console and navigate to Library | Templates. Open the Change Request Service Pack Installation Template that we created in an earlier recipe.
How to do it...
Follow these steps to create a Sequential Activity:
Click on the Activities tab in the Change Request form.
Open the Parallel Activity we created in the previous recipe. (Right-click on the title of the Parallel Activity and select Open.
Click on the Activities tab in the Container Activity Template form.
Click on the + Activities...