Assessment exam answers (Chapter 14)
Question 1
Which of the following would not be considered a subsidiary plan of the project management plan?
- Risk management plan
- Scope baseline
- Cost management plan
- Quality management plan
The scope baseline is part of the project management plan; however, it isn't a subsidiary plan.
Question 2
You and your team have put together a comprehensive project management plan and you feel it will be executed effectively. What do you need to do before you can begin executing project work?
- Hold a kick-off meeting.
- Acquire your resources.
- Gain formal approvals.
- Communicate the plan to your customer.
In this case, there may be several things you will do, including carrying out a kick-off meeting and explaining the plan to your customer. The project management plan needs to be formally bought into and accepted before you can begin execution.
Question 3
What is the main output of direct...