Exploring the management areas
In Chapter 1, I introduced the key management areas: plan, risk, and stakeholder management. Using the Mercury program as an example, we’ll examine each of these in a bit more depth and continue to build upon our use case study.
Project plan
Let’s examine the Windows rollout project plan in a bit more detail. At this point in the book, we’ll assume a few things:
- We have as much resourcing as we need (so, everything that can technically start at the beginning of the project will be scheduled to start)
- No resource timing constraints exist
- Estimates are uniform across all platforms
- All predecessors are considered finish-to-start (meaning the predecessor must be finished before the task can start)
- There are no inter-project dependencies
- In other words, a textbook program example!
Given these assumptions, Table 3.2 lists a simplified project plan for the Windows project: