- You are the project manager for a large development project and are discussing budgeting with your sponsor. The sponsor is asking for a definitive estimate from you to properly allocate funds for the project. Which of the following estimating techniques will give you a definitive estimate?
- Analogous
- Parametric
- Bottom-up
- Three-point
- Which of the following could be considered the costs of quality? Choose all that apply:
- Training
- Appraisal
- Resource rates
- Scope creep
- Formal change control
- Prevention costs
- You and your team have reached a milestone on your project, and your senior stakeholders will be signing-off on the quality of the work and the project’s progress. These formal processes are known as which of the following?
- Quality gate
- Phase gate review
- Governance gate
- Go / no go decision
- As a project manager, your responsibility is to put together a comprehensive...
United States
Great Britain
India
Germany
France
Canada
Russia
Spain
Brazil
Australia
Singapore
Hungary
Ukraine
Luxembourg
Estonia
Lithuania
South Korea
Turkey
Switzerland
Colombia
Taiwan
Chile
Norway
Ecuador
Indonesia
New Zealand
Cyprus
Denmark
Finland
Poland
Malta
Czechia
Austria
Sweden
Italy
Egypt
Belgium
Portugal
Slovenia
Ireland
Romania
Greece
Argentina
Netherlands
Bulgaria
Latvia
South Africa
Malaysia
Japan
Slovakia
Philippines
Mexico
Thailand