Assessment questions
Question 1: Which of the following would not be considered a subsidiary plan of the project management plan?
- Risk management plan
- Scope baseline
- Cost management plan
- Quality management plan
Question 2: You and your team have put together a comprehensive project management plan and you feel it will be executed effectively. What do you need to do before you can begin executing project work?
- Hold a kick-off meeting.
- Acquire your resources.
- Gain formal approvals.
- Communicate the plan to your customer.
Question 3: What is the main output of direct and manage project work?
- Issue log
- Change requests
- Work performance data
- Deliverables
Question 4: Your team is in the process of executing project work and gathering information that allows you to make decisions about project changes to be made, and it gives the team the ability to communicate with stakeholders in the form of work performance...