Chapter 3 – The Scrum Team
Answers
- The correct answer is d.
The Developers are self-managing and they are solely responsible for deciding how to deliver a Product Increment and which working practices to employ. Neither the Scrum Master, nor the Product Owner may interfere with the Developers' work.
- The correct answer is b.
Answer (d) is wrong, as the Developers estimate and select work items at the start of the Sprint and then commit to completing them.
(a) and (c) are also wrong as the Scrum Master cannot interfere with the Developers' working practices.
The Scrum Master may, however, guide them towards customizing or improving the Scrum process and suggesting a Sprint length increase (b) provides such guidance.
- The correct answer is b.
Answer (a) is clearly wrong, and (d) is the responsibility of the Scrum Master. The Product Owner does not manage the project, or the work being done, they are responsible for the product (c).
- The correct answer is...