Question 1
You are working with your stakeholders to determine what information they need to be updated on weekly. One of your key stakeholders, Joan, has asked to be kept up to date on any surprises that occur on the project that result in a negative impact. Which of the following documents is Joan asking to see weekly?
- The stakeholder register
- The risk management plan
- The issue log
- The assumption log
Question 2
Which of the following documents can help you plan for stakeholder engagement on the seller side of the project?
- Agreements
- SOW
- RFP
- The procurement plan
Question 3
Power structures, politics, and how communication flows in your organization are influenced by which of the following?
- Enterprise environmental factors
- The industry
- The organizational setup
- Organizational process assets
Question 4
You are a project manager working on a large construction project and...