Assessment exam answers (Chapter 2)
Question 1
Which of the following is not an enterprise environmental factor?
- Organizational culture, structure, and governance
- Marketplace conditions
- Government or industry standards/regulations
- Organizational knowledge bases
Organizational knowledge bases are considered an organizational process asset.
Question 2
Kathy is a newer project manager and is attempting to determine which plans to create to manage her project effectively. She knows that she will need an integrated project management plan to understand how to manage the project. Which of the following would not be included in the project management plan and instead could be considered a project document?
- Stakeholder engagement plan
- Issue log
- Life cycle approach
- Project charter
The issue log is a project document that is updated regularly. Issues are prevalent in projects and therefore wouldn't benefit from formal change...