Assigning test results to work items
Once the test has run automatically and the build process has finished, you can assign the results to work items that have been added to the backlog and sprint. For this, you must perform the following steps:
- Go back to the build pipeline and select the pipeline that ran last. Click Test from the top menu.
- For the results table, make sure that Passed is selected and that Failed and Aborted have been deselected:
- Then, select a couple of tests. After doing this, from the top menu, click Link:
- Search for
As a tester
and select the work item that is displayed as a search result: - Click Associate to link the work item to the test result.
- Now, click on one of the test results that's linked to the work item. This will show the details for this item. From here, you can click on work items from...