Project tracking flowchart
A complete flowchart for the project tracking process is depicted in the following flowchart. Setting the baseline is a foundational activity for project tracking. Subsequently, the project manager will establish the tracking frequency and data collection format. Once within the execution phase, every project update thereafter is cyclic:
There are a few important points to be noted about the steps in this flowchart, as follows:
- The first step of project tracking is to set the status date. Your project schedule will be updated until this date. This is explained further in the next section.
- The next step is to gather task information for completed tasks and in-progress tasks from your team.
- Update the schedule with tracking information. This is the key topic of this chapter.
- If your project is off the acceptable track limits, then you have to reschedule the tasks...