Search icon CANCEL
Arrow left icon
Explore Products
Best Sellers
New Releases
Books
Videos
Audiobooks
Learning Hub
Conferences
Free Learning
Arrow right icon
Arrow up icon
GO TO TOP
The Professional Scrum Master Guide

You're reading from   The Professional Scrum Master Guide The unofficial guide to Scrum with real-world projects

Arrow left icon
Product type Paperback
Published in Jul 2021
Publisher Packt
ISBN-13 9781800205567
Length 174 pages
Edition 1st Edition
Tools
Concepts
Arrow right icon
Author (1):
Arrow left icon
Fred Heath Fred Heath
Author Profile Icon Fred Heath
Fred Heath
Arrow right icon
View More author details
Toc

Table of Contents (16) Chapters Close

Preface 1. Section 1:The Scrum Framework
2. Chapter 1: Introduction to Scrum FREE CHAPTER 3. Chapter 2: Scrum Theory and Principles 4. Chapter 3: The Scrum Team 5. Chapter 4: Scrum Events 6. Chapter 5: Scrum Artifacts 7. Section 2:Scrum in Action
8. Chapter 6: Planning and Estimating with Scrum 9. Chapter 7: The Sprint Journey 10. Chapter 8: Facets of Scrum 11. Section 3:The PSM Certification
12. Chapter 9: Preparing for the PSM I Assessment 13. Assessments 14. Other Books You May Enjoy 15. Index

Chapter 6 – Planning and Estimating with Scrum

Answers

  1. The correct answer is c.

    Story points are used to indicate relative size and complexity. They do not denote time units. It is impossible to know whether an item is feasible to be completed within a Sprint, based on its story points, unless we know the estimation scale and baseline.

  2. The correct answers are a, c, and d.

    Having fixed dates in the product roadmap goes against Agile and Scrum principles of constant inspection and adaptation versus following a set plan.

  3. The correct answer is c.

    Estimating methods such as planning poker rely on developers reaching consensus by providing individual estimates and then discussing the motivations behind the estimates until agreement is reached on a single estimate value.

  4. The correct answer is c.

    Velocity is subjective to a specific team and product. It is not a comparative measurement.

  5. The correct answer is b.

    Burn-up charts let us visualize progress over time....

lock icon The rest of the chapter is locked
Register for a free Packt account to unlock a world of extra content!
A free Packt account unlocks extra newsletters, articles, discounted offers, and much more. Start advancing your knowledge today.
Unlock this book and the full library FREE for 7 days
Get unlimited access to 7000+ expert-authored eBooks and videos courses covering every tech area you can think of
Renews at $19.99/month. Cancel anytime