Settings at the activity level
Last but certainly not least, the activity level settings are paramount for schedule calculations. Most people know the activity settings and forget to look into all other settings when dates do not seem to calculate as expected.
Activities are the major component of a schedule, and there are several aspects to each activity that must be considered. Activity components can be categorized as Mandatory or Optional, and several of them together represent the chain that affects dates in P6.
Activity components that affect schedule calculation:
MANDATORY |
Affects Dates |
OPTIONAL |
Affects Dates |
---|---|---|---|
WBS and OBS |
Expenses | ||
Activity ID and Description |
Steps | ||
Activity Type |
Yes |
Notebooks/Feedback | |
Duration |
Yes |
WP & Documents | |
Date (input) |
Yes |
Activity Codes | |
Calendar Assignments |
Yes |
Relationships |
Yes |
Duration Type |
Yes |
Constraints |
Yes |
Percent Complete Type |
Yes |
Role and Resource Assignments |
Yes |
Activity types
Each type will react differently to scheduling...