Search icon CANCEL
Arrow left icon
Explore Products
Best Sellers
New Releases
Books
Videos
Audiobooks
Learning Hub
Conferences
Free Learning
Arrow right icon
Arrow up icon
GO TO TOP
CompTIA Project+ Certification Guide

You're reading from   CompTIA Project+ Certification Guide Learn project management best practices and successfully pass the CompTIA Project+ PK0-004 exam

Arrow left icon
Product type Paperback
Published in Sep 2018
Publisher Packt
ISBN-13 9781789534498
Length 358 pages
Edition 1st Edition
Arrow right icon
Author (1):
Arrow left icon
Ashley Hunt Ashley Hunt
Author Profile Icon Ashley Hunt
Ashley Hunt
Arrow right icon
View More author details
Toc

Table of Contents (13) Chapters Close

Preface 1. Introduction to the CompTIA Project+ Exam (PK0-004) 2. Project Initiation FREE CHAPTER 3. Project Roles and Responsibilities 4. Developing a Project Charter 5. Creating a Work Breakdown Structure (WBS) 6. Developing a Project Schedule 7. Resource Management Planning and Communication Considerations 8. Budget and Contingency Plans for Risk 9. Monitoring and Controlling Project Work 10. Formal Project or Phase Closure and Agile Project Management 11. Assessments 12. Other Book You May Enjoy

Questions

  1. You are the project manager for a large development project and are discussing budgeting with your sponsor. The sponsor is asking for a definitive estimate from you to properly allocate funds for the project. Which of the following estimating techniques will give you a definitive estimate?
    • Analogous
    • Parametric
    • Bottom-up
    • Three-point
  2. Which of the following could be considered the costs of quality? Choose all that apply:
    • Training
    • Appraisal
    • Resource rates
    • Scope creep
    • Formal change control
    • Prevention costs
  3. You and your team have reached a milestone on your project, and your senior stakeholders will be signing-off on the quality of the work and the project’s progress. These formal processes are known as which of the following?
    • Quality gate
    • Phase gate review
    • Governance gate
    • Go / no go decision
  4. As a project manager, your responsibility is to put together a comprehensive...
lock icon The rest of the chapter is locked
Register for a free Packt account to unlock a world of extra content!
A free Packt account unlocks extra newsletters, articles, discounted offers, and much more. Start advancing your knowledge today.
Unlock this book and the full library FREE for 7 days
Get unlimited access to 7000+ expert-authored eBooks and videos courses covering every tech area you can think of
Renews at $19.99/month. Cancel anytime