Creating and personalizing Change Management Parallel Activities
Activities in SCSM 2016 are executed sequentially by default. To run different activities in parallel we need a Parallel Activity container.
This recipe will show how to create and work with Parallel Activities in SCSM 2016.
Getting ready
To create Parallel Activities in a Change Request Template open the SCSM 2012 console and navigate to Library | Templates. Open the Change Request Service Pack Installation Template that we created in an earlier recipe.
How to do it...
The following steps describe how to create and personalize Parallel Activities:
Click on the Activities tab in the Change Request form.
Click on + Activities.
Choose the Default Parallel Activity from the list of templates and click on OK.
In the General tab we will fill the Title and Description field. We will select Software from the Area drop-down box.
Click on the Activities tab.
Add Manual Activities to the Container Activity Template. In this recipe we add the...