- You are the project manager for a large development project and are discussing budgeting with your sponsor. The sponsor is asking for a definitive estimate from you to properly allocate funds for the project. Which of the following estimating techniques will give you a definitive estimate?
- Analogous
- Parametric
- Bottom-up
- Three-point
- Which of the following could be considered the costs of quality? Choose all that apply:
- Training
- Appraisal
- Resource rates
- Scope creep
- Formal change control
- Prevention costs
- You and your team have reached a milestone on your project, and your senior stakeholders will be signing-off on the quality of the work and the project’s progress. These formal processes are known as which of the following?
- Quality gate
- Phase gate review
- Governance gate
- Go / no go decision
- As a project manager, your responsibility is to put together a comprehensive...